New Valley Station

Investing in the Future

After More Than 70 Years, the Herzogstandbahn Gets a New Valley Station

Herzogstandbahn GmbH is setting the course for a sustainable future: On the existing premises, the current valley station is scheduled to be replaced by a new, energy-efficient, and partially accessible building by November 2027. The Herzogstandbahn’s cable car technology, route, and mountain station will remain unchanged. Furthermore, the construction of the new valley station alone will not result in an increase in the number of passengers transported. Rather, the focus is on functional and qualitative improvements—offering greater comfort, higher efficiency, and partially accessible entry for guests and employees.

Accessible. Forward-thinking. Cost-effective.

The new valley station will feature an open, bright, and inviting design, with a consistent focus on comfort and accessibility for all guests. The entire area is designed to be step- and threshold-free, thereby providing largely barrier-free access. More spacious entry areas to the cable car cabins ensure greater freedom of movement and a relaxed experience. The entrance area will be equipped with seating and invites visitors to linger, while the ticket counter area is clearly structured to facilitate a smooth flow of traffic. In the future, ticket sales via vending machines will also be offered as an option to provide additional flexibility. The restroom facilities will also be completely renovated and modernized—designed to be accessible, family-friendly, and equipped with contemporary amenities.

The overall concept for the new valley station is firmly rooted in sustainable energy supply—utilizing heat pumps and solar energy—as well as resource-efficient operations. The use of state-of-the-art building technology and materials will result in significant CO₂ reductions, making an important contribution to energy-efficient and future-oriented operations.

A clear statement for the region.

The existing Herzogstandbahn valley station was built in 1954 along with the chairlift and was only partially adapted to the operation of today’s gondola lift during the 1994 renovation. After more than 70 years, however, the building no longer meets current requirements—neither for the approximately 155,000 guests per year nor for the employees in daily operations. As part of the project, the lease agreement with the Bavarian State Forests is also set to be extended early for an additional 50 years. Negotiations on this matter are in the final stages.

The total cost amounts to approximately 5.5 million euros and will be financed through the Herzogstandbahn’s solid financial and earnings strength, without public subsidies.

Schedule. Construction Phase. Operations

Construction work on the new valley station will begin on October 26, 2026. Following the 2026/2027 fall maintenance period, cable car operations are expected to resume around Pentecost 2027. The work will be organized so that key parts of the building can be completed while operations continue, minimizing disruptions to passenger service in the summer of 2027. Completion and the grand opening of the new valley station are scheduled for November 2027.